Status Indicators for Most Recently Reported Results: On Target | Caution | Below Plan | No Information
Actual | Target | Results for |
Goal:
Complete construction of the Moss Valley Sewer line by 2025
50.00% | 50.00% | Mid-Year 2024 |
Definition
The City of Bartlett, currently discharges a portion of the Fletcher Creek Sewer Basin to Memphis via the Moss Valley Sewer Line. As a part of the City of Memphis Sewer Study, it was discovered that the Moss Valley Sewer line is currently undersized. The City of Bartlett contracted with Barge Design Solutions to produce a set of Construction plans for the installation of a larger sewer replacement line. This upsized line installation will allow the City of Bartlett to spur development within this sewer sub-basin.
Analysis
This project involves developing construction plans, acquiring easements, bidding the project, and constructing it. The City of Bartlett has evaluated sewer flows, developed a construction plan, acquired the necessary easements, and now needs to broadcast a formal bid for the project. The City is presently 50% complete with the milestones necessary to finish the project and is expected to be complete by the end of 2025.