Replace the identified Sewer Pump Stations by 2026 .
40.00% | 40.00% | 2024 |
Definition
The City of Bartlett is responsible for maintaining 28 pump stations and 341 miles of sewer pipe within the City limits. This collection system transports sewer to treatment plants within the City as well as to the City of Memphis.
Analysis
The City contracted with Allen & Hoshall Engineering to produce construction plans to replace the City's four largest sewer pump stations, which are approaching the end of life. The construction contract was awarded to Chris Hill Construction in January 2025. Work on this project will begin mid-April of 2025 with an expected completion date of July 2026.