% of plant evaluation and rehabilitation plan completed
Actual Target Results for

Goal:

Construct and complete a rehabilitation plan for all Water & Wastewater Treatment Plants by 2027.

15.00% 25.00% Mid-Year 2024

Definition

The City of Bartlett currently maintains four (4) Water Plants and two (2) Wastewater Plants. The City's Water Treatment Plants collect, treat, and distribute water supplies to residents, businesses, and industrial users. The City's Wastewater Treatment Plants incur the additional responsibility of removing contaminants and suspended solids from wastewater. These plants are aging, and persistent measures are needed to ensure they continue operating at an optimum level.

Analysis

The City has completed an inventory of all existing water plants and is currently working on upgrading one (1) Water Plant in FY2025, with bid selection and construction slated to begin in the Fall of 2024. 

The City is also working with Path Company to conduct a feasibility study of its Wastewater Treatment Plants to identify and analyze opportunities for measurable economic efficiencies. This evaluation should be completed by the Fall of 2024. 