Homepage > Growth & Infrastructure >  % project completed >

 

Status Indicators for Most Recently Reported Results: On Target | Caution | Below Plan | No Information

% project completed
Actual Target Results for

Goal:

Complete construction of the Moss Valley Sewer line by 2025

60.00% 75.00% Q4-24

Definition

The City of Bartlett, currently discharges a portion of the Fletcher Creek Sewer Basin to Memphis via the Moss Valley Sewer Line.  As a part of the City of Memphis Sewer Study, it was discovered that the Moss Valley Sewer line is currently undersized.  The City of Bartlett contracted with Barge Design Solutions to produce a set of Construction plans for the installation of a larger sewer replacement line.  This upsized line installation will allow the City of Bartlett to spur development within this sewer sub-basin. 

Analysis

The City of Bartlett has assessed sewer flows, developed a construction plan, acquired the necessary easements, completed the formal bidding process, and awarded the project to Enscor. Although the City has faced a few unexpected challenges in starting construction, plans are in place to begin in early spring, with the goal of completing the project by July 2025. This critical project will unlock over 38 acres of prime real estate adjacent to the Union Depot development.

CONTACT INFORMATION
City of Bartlett
6400 Stage Road
Bartlett, TN 38134
Debbie Gelineau
[email protected]